Our Process
Step by Step
We never build the same home twice.
Each design begins with a fresh perspective.
Feasibility
Discuss your “program,” including needs, wants, and budget. This meeting ensures feasibility and initiates design.
Onboarding
Design agreement extends for up to 120 days days to allow time to design home and move to contract
Unique
With lot specific designs, we carefully assess each site’s features to emphasize its strengths and optimize the overall design.
Timing Overview
- Design Agreement
- 120 days to Contract
- 12-16 weeks from Contract for Engineering
- 4-5 wks for Truss Design/Review
- 2-4 wks for Structural Engineering
- 30-45 days for Permitting
- Permit is Ready
- Begin foundation work
- 10-14 months from Issuance of Permit to Turnover